Bullet practice undertaking gathers pace

Work on India’s first high-speed bullet practice, which guarantees to hurry up journey between Ahmedabad and Mumbai at 320 km per hour, is continuing at an identical livid tempo. The ₹25,000-crore allocation within the interim Finances 2024-25 — one of many highest ever in recent times — is one more signal of the significance the central authorities accords to the undertaking, which is anticipated to launch providers between Ahmedabad (Gandhi Ashram station) and Mumbai (Bandra-Kurla Advanced station) round 2026-27.
  • Additionally learn: Ahmedabad Metro to attach GIFT Metropolis & Gandhinagar by June 2024

The proposed budgetary outlay is 35 per cent larger than the revised estimates of FY24 at round ₹18,600 crore. The price range estimates for FY24 was ₹19,600-odd crore with help from inner and extra-budgetary assets at ₹20,592 crore.

In FY23, the Nationwide Excessive-Pace Rail Company Restricted (NHSRCL) — a special-purpose car created for the undertaking by the railway ministry, which holds 50 per cent fairness, and the state governments of Gujarat and Maharashtra, which maintain 25 per cent fairness every — had budgetary help of ₹12,000 crore.

The inspiration stone for the Mumbai-Ahmedabad high-speed rail undertaking was laid in September 2017 by Prime Minister Narendra Modi and his Japanese counterpart Shinzo Abe.

On January 24 this 12 months, Railways Minister Ashwini Vaishnaw posted on X (previously Twitter) that land acquisition for the bullet practice undertaking was “100 per cent full”, and 274.12 km of pier casting and 127.72 km of girder launching had been accomplished.

Value break-up

The preliminary estimate for the undertaking price was ₹1.08 lakh crore

The 508-km high-speed rail hall will traverse about 350 km in Gujarat and 156 km in Maharashtra.

In November 2023, it was introduced that NHSRCL had accomplished 100 km of viaduct and 250 km of pier work.

A smooth mortgage prolonged by Japan Worldwide Cooperation Company (JICA) will assist fund 81 per cent of the development price, with the remaining coming by NHSRCL.

Till December 2023, the standing of fairness contribution for the undertaking confirmed approval for ₹20,000 crore, which incorporates ₹10,000 crore from the railway ministry and ₹5,000 crore every from the Gujarat and Maharashtra governments. Whereas the ministry and the Gujarat authorities have paid their share in full, Maharashtra has paid solely ₹6 crore until date.

Progress report

The December report on the progress of the bullet practice undertaking, accessed by businessline, reveals that work within the Maharashtra part was accomplished to the tune of twenty-two.03 per cent, whereas it was 47.44 per cent in Gujarat. So the general completion stands at 39.12 per cent.

The report mentions completion of land acquisition in Gujarat, Dadra and Nagar Haveli, and Maharashtra. Almost 81 per cent of the acquired land in Maharashtra is below the possession of the SPV, it provides.

In line with railway officers, all of the 11 civil tender packages throughout Gujarat and Maharashtra have been awarded.

“The problem of Grasp Implementation Plan was mentioned and the Japanese facet indicated that phased commissioning in Gujarat (Vapi-Sabarmati part) in Aug 2027, as a standard goal between Japan and India, may very well be thought-about…” the report says.

Financially the progress stands at 44.36 per cent, a senior railway official mentioned, requesting anonymity. Of the roughly ₹54,000 crore raised to this point, ₹11,400-odd crore is the extent of capital utilisation through the present fiscal (FY24). Spending throughout December 2023 was to the tune of ₹1,173 crore, in line with the report.

Vaishnaw had earlier mentioned that political variations with the erstwhile Uddhav Thackeray authorities in Maharashtra had delayed work on the bullet practice undertaking, together with land acquisition, floating of tenders, award of contracts and so forth. “There may be substantial progress within the phase now,” he mentioned just lately.

Japanese issues

In line with the undertaking’s progress report, the Japanese facet has, in October 2023, initiated worth negotiations with a sole bidder for {the electrical} works. The deadlines for operationalising numerous sections of the undertaking embrace Surat-Bilimoria by July 2026 and Sagarmati-Vapi by August 2027.

  • Additionally learn:L&T baggage Mumbai-Ahmedabad high-speed rail undertaking; inventory inches up

The detailed design for signalling and telecom (S&T) has been accomplished by the Japanese facet. It has determined to put early orders for long-lead S&T gear resembling automated practice management, digital interlocking, monitor circuits, level machine equipment, cab radio, and so forth for the 12 stations on the route.

“For these early orders, 5 separate packages are deliberate and contracts can be awarded on to OEMs [original equipment manufacturers], as per the Japanese practices. Award of those contracts is anticipated by Feb 2024,” the report mentions.